--- In AsburyPark@yahoogroups.com, "Fred" <[EMAIL PROTECTED]> wrote:
>
> > >
> > >
> That's the problem the City didn't want any work done on the 
building 
> during the summer. They wanted to keep the stores open. That's why 
its 
> a two phase deal. That wasn't the Partners idea.
> 
I never accused the city of genius. Yes, but that was when? You 
should be able to do it between Labor and Memorial Day.

The Dispute Resolution Agreement is dated April 10, 2006. That is 
when it was final, but even taking that date, you should be ready to 
go with construction on the day after Labor Day. WHen I said no 
stores during the summer, I meant this summer in order to be able to 
meet the october 2007 deadline, which I think is very difficult to 
do. Stop picking apart things. What is at issue is that Partners did 
not, and obviously cannot, live up to the DRA with regard to the 5th 
Ave pavillion, and I suspect most of the other elements as well. 
Isn;t the Casino to have a new roof by October 2007 as well?





 
Yahoo! Groups Links

<*> To visit your group on the web, go to:
    http://groups.yahoo.com/group/AsburyPark/

<*> Your email settings:
    Individual Email | Traditional

<*> To change settings online go to:
    http://groups.yahoo.com/group/AsburyPark/join
    (Yahoo! ID required)

<*> To change settings via email:
    mailto:[EMAIL PROTECTED] 
    mailto:[EMAIL PROTECTED]

<*> To unsubscribe from this group, send an email to:
    [EMAIL PROTECTED]

<*> Your use of Yahoo! Groups is subject to:
    http://docs.yahoo.com/info/terms/
 

Reply via email to