Don Cragun wrote:
> OK.  After discussing this further with the project team and management
> the following changes are being made to this case:
> 
> 1.  There will be no link (neither hard nor symbolic) between top and
>     prstat.
> 2.  The real top utility will be supplied rather than changing prstat.
> 3.  The top utility will be delivered through the SFW consolidation
>     rather than through the ON consolidation.
> 4.  There is no commitment at this time to do a phase 2.  If there is a
>     phase 2, it will extend top options to provide capabilities similar
>     to those provided by the current prstat that are not yet provided
>     by top.
> 5.  The project team will have to get legal approval for the unixtop
>     license (but that is not an ARC issue).
> 
> This FastTrack remains running and the timeout remains the same.

Given all the above this case should be marked as withdrawn sine nothing 
in the case is valid for the new proposal. A new case for delivering top 
should be started.

-- 
Darren J Moffat