"but in two weeks, 1,500 workstation and 2,000 users
will be converted all at the same time."
FWIW, we've migrated around 10,000 user accounts and
probably 6,000 workstations. We typically did them in batches over several
months. I think the most we did in one batch was ~500 users and ~200
workstations. A couple of weeks ago we had 2,500 user accounts to migrate, and
tried it in one chunk. Things started to crumble, with passwords not migrating
and group memberships not updating. We ended up backing down to several groups
of about 500, and things ran fine. We're guessing that the NT 4 domain
controller hardware wasn't up to the task (old, old beater boxes), but don't
know for sure that was the problem.
I'd strongly suggest breaking up your 1,500
workstations and 2,000 users into several batches for migration purposes,
even if you're going to do all of the batches in one
night/weekend.
Hunter From: Bell, Stephen [mailto:[EMAIL PROTECTED] Sent: Monday, March 29, 2004 9:17 AM To: [EMAIL PROTECTED] Subject: RE: [ActiveDir] Quick question on ADMT
|
Title: Message
- [ActiveDir] Quick question on ADMT Bell, Stephen
- RE: [ActiveDir] Quick question on ADMT Eric Fleischman
- RE: [ActiveDir] Quick question on ADMT Bell, Stephen
- RE: [ActiveDir] Quick question on ADMT Eric Fleischman
- RE: [ActiveDir] Quick question on ADMT Bell, Stephen
- RE: [ActiveDir] Quick question on ADMT Eric Fleischman
- RE: [ActiveDir] Quick question on ADMT Coleman, Hunter
- RE: [ActiveDir] Quick question on ADMT Bell, Stephen