Claudio,

Since you only have one node, the only way to have more than one migration
process is to turn on collocation for you tape pool at the filespace level.
This will cause each filespace on the client to migrate to a separate tape.
If you only have one filespace on the client, your out of luck.

Laura Buckley
SSSI


-----Original Message-----
From: ADSM: Dist Stor Manager [mailto:[EMAIL PROTECTED]]On Behalf Of
Claudio Cofre Caro
Sent: Tuesday, June 12, 2001 4:18 PM
To: [EMAIL PROTECTED]
Subject: only one migration process :-(


Hi, anybody know how resolve thist ?  :

I have TSM 4.1.3 on WinNT4.0 in Server to Server configuration with only
one node in the target server (the node is the source server).

In the Target Server when the disk migration begin, i have only one
migration process that use only one drive, and the others drives still
empties (i have other 2 drives that still unused).

Anyone know how can i used my three drives at the same time with this
configuration?

thanks in advance...

-----------------------------------------------
             Claudio Cofri Caro
             Ingeniero Especialista de Producto
             S&A Consultores - Chile
             Fono  : +56 (2) 235-0289 ext 301
             Fax   : +56 (2) 235-0288
             e-mail: [EMAIL PROTECTED]

Reply via email to