On Dec 10, 2008, at 22:29 , Thomas Denier wrote:
We have a 5.4.2.0 TSM server running under mainframe Linus. Our daily housekeeping uses 'backup stgpool', 'migrate stgpool', and 'reclaim stgpool' commands that start multiple processes. The home-grown software that manages our housekeeping figures out when each of these activities is done by examining data piped from an administrative client session with the console option. I am looking into the possibility of simplifying the management software by using the 'wait=yes' option of the various commands. How does this option behave with multiple processes? In particular, does the command end when the last of the multiple processes ends?
`look into the PARALLEL and SERIAL keywords for TSM server scripts. -- Met vriendelijke groeten, Remco Post [EMAIL PROTECTED] +31 6 248 21 622