If they have their own shed, and their own 25G on the property, they
have some sort of extraordinary arrangement with AT already. They should
not get you involved in what they want to "enhance", they should deal
directly with AT.
bp
<part15sbs{at}gmail{dot}com>
On 7/6/2016 9:55 AM, That One Guy /sarcasm wrote:
We have a customer with equipment on an American Tower property. They
have their own shed on the property with a 20' 25 g tower attached.
They have us and a second WISP on their 25g, but our service requires
another 10-30 feet depending on how much better they want the service
They want us to do the tower. I told the bosses absolutely not without
some sort of build permit directly from American Tower.
Am I being a dick about this?
--
If you only see yourself as part of the team but you don't see your
team as part of yourself you have already failed as part of the team.