Hello all,
I am new to Amanda. Maybe my question will sound a bit silly but I have
to
ask, because an uncountable number of time I've seen in the
documentation
and in messages in this mailing list runspercycle set with a value of 5
and
immediately next to it (like a golden rule) the mention that amdump will
run 5 times per cycle excluding weekends?
My question is: why excluding weekends? Is not possible to run amdump 5
times per week
excluding Wednesday and Friday? Is there any correlation between the
value
5 and the weekends?
Another related question: In a configuration with
dumpcycle 7 days
runspercycle 5
during a dumpcycle (a week) do I have to run amdump in the same days as
in the
previous dumpcycle or in the first dumpcycle I can run amdump during the
days
1 2 4 5 6
and in the second dumpcycle amdump can be run during the days
2 3 4 6 7?
Regards
Cristian