It looks like you know this but I wanted to make sure. It is not just
workflow that is affected but existing data as well. Everything that was
showing up as "completed" will now show up as "on hold".

-----Original Message-----
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of mahalaksmi Ramakrishnan
Sent: Friday, October 20, 2006 2:09 AM
To: arslist@ARSLIST.ORG
Subject: Need Solution

Hi all,

Assume there are four status new,assigned,work in progress and
completed.(
Note: new =0,assigned =1, WIP =2, completed =3)

Many workflows are written with these status. Now i have to add a status
"on hold" between work in progress and completed.

If i add on hold then the onhold status position will become 3 which
will affect the completed status.

Is there any way to add on hold inbetween WIP and Completed without
affecting both (WIP and Completed) status of existing workflow.

________________________________________________________________________
_______
UNSUBSCRIBE or access ARSlist Archives at http://www.wwrug.org

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at http://www.wwrug.org

Reply via email to