Replace the "subordinate" escalations with filters.

 

For example, I assume you have something like this now:

 

Escalation 1 fires at 12:00

Escalation 2 fires at 12:15 but is dependent on 1's success

 

What I suggest is replace Escalation 2 with a filter.  Set that filter
to run on modify and have it look for the expected value set by
Escalation 1.

 

HTH,

Norm

 

________________________________

From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of Alfonso Eric B Contr 95
CG/SCCSS
Sent: Monday, April 30, 2007 12:41 PM
To: arslist@ARSLIST.ORG
Subject: Forcing escalations to run in sequence and not starting until
previous is completed

 

Hi everyone,

 

I am new to Remedy development and recently completed a full active
directory integration with Remedy v.7.  It takes several escalations
running in sequence each night to keep the various location and people
related forms updated.  I have the escalations running at pre-determined
times in sequence.  Is there any way to set one escalation to trigger
the start of the next which will trigger the start of the next, etc,
without using the time as the trigger?  There are times when the
previous escalation fails and I would like it to prevent the next one
from firing when this occurs.  

 

Thank you,

 

Eric Alfonso, Contractor, 95 CG/SCCSS 
DSN 525-9192 
COMM 661-275-9192 
Remedy Support Team 
[EMAIL PROTECTED] <mailto:[EMAIL PROTECTED]>


__20060125_______________________This posting was submitted with HTML in
it___

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org ARSlist:"Where the 
Answers Are"

Reply via email to