I have CM 7.0.3 P9, and am seeing something that doesn't make sense.  So
either it isn't working as designed, or I don't understand the design.

After the Business Approval is processed, the Status is Scheduled.  In
either case, the PF Bar should allow the Change User at that point to select
"Next Stage" from the PF Bar to move that into a Status of "Implementation
in Progress".  This is not working.  I can change the Status manually, but
not from the PF Bar.

The same is true when attempting to use the PF Bar from "Planning in
Progress" to "Scheduled for Review".  Manually, it works just fine.  With
the PF Bar, not so much.

Both processes use the same part of the PF Bar.  Is this a known issue with
a resolution, or just something we are going to have to work around, or is
this "As designed".

Rick

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor:[email protected] ARSlist: "Where the Answers Are"

Reply via email to