Hi,
You can try the following steps to achieve the requirement:
--Disable the OOTB filter : TMS:TAS:ActiveToPendingAssigned
--Change the Run-If qualification of TMS:TAS:ActiveToAssigned to
('DB.Status' = "Staged") AND ('TR.State' = "Active") AND ('TaskType' =
"Manual")
Hope this will help you.
--
Regards,
Prathamesh S.
Vyom Labs Pvt. Ltd.
BSM Solutions & Services || ITIL Consulting & Training
Email: [hidden email]
<http://ars-action-request-system.1093659.n2.nabble.com/user/SendEmail.jtp?t
ype=node&node=7583733&i=0> || Web Site: www.vyomlabs.com Follow Vyom Labs
http://twitter.com/#!/vyomlabs <http://twitter.com/#%21/vyomlabs> ||
http://www.linkedin.com/company/vyom-labs
From: Action Request System discussion list(ARSList)
[mailto:[email protected]] On Behalf Of Brittain, Mark
Sent: Tuesday, October 15, 2013 11:58 PM
To: [email protected]
Subject: Template Assignment Flow
**
Hi All,
I have been experimenting with Tasks/Templates/Group Templates for a good
chunk of the day and have not been able to get the desired flow. Basically I
want to create a Work Order, use a Task Group Template and then once the
Status of the Work Order is set In-Progress, the tasks are assigned one at a
time in order without further human intervention.
I am doing this with Work Orders but should apply to the other applications.
I want to create 5 Task Templates and put them in a Task Group Template,
sequenced 1-5. Each Task is for a different Assigned Group and the Assignee
is blank. Can't use the assignment engine to assign to a person.
What happens OOB: When the status of Work Order to In-Progress, the Status
of the first Task changes to Pending/Assignment and 2-5 are Staged. Then
someone has to set the Status to Assigned. Once the first Task is Closed,
the second becomes Pending/Assignment and someone has to assign that one
out. Same for tasks 3-5.
What I need to have happen: When the status of Work Order to In-Progress,
the Status of the first Task changes to Assigned and 2-5 are Staged. Then
when the first Task is Closed, the second becomes Assigned. Same for tasks
3-5.
Is that possible? I would think so and I am just not getting what the guide
is saying.
ARS 7.6.04 SP3
ITSM 7.6.04 SP3
Thanks
Mark
_____
This E-mail and any of its attachments may contain Time Warner Cable
proprietary information, which is privileged, confidential, or subject to
copyright belonging to Time Warner Cable. This E-mail is intended solely for
the use of the individual or entity to which it is addressed. If you are not
the intended recipient of this E-mail, you are hereby notified that any
dissemination, distribution, copying, or action taken in relation to the
contents of and attachments to this E-mail is strictly prohibited and may be
unlawful. If you have received this E-mail in error, please notify the
sender immediately and permanently delete the original and any copy of this
E-mail and any printout.
_ARSlist: "Where the Answers Are" and have been for 20 years_
_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
"Where the Answers Are, and have been for 20 years"