Hi Benny, These are the steps: 1. Run forecast scheduling. 2. Run Master scheduling - you can run both with finite (RCCP) or infinite (CRP)capacity. 3. go to the specific work center, and then see the load. 4. If capacity is more than the availability, try to use work center task group to level the load. 5. Run the master scheduling again if necessary to see the effect of work center task group.
Hope it will helps Fajar Hidayat Axapta Solutions Services Dept -----Original Message----- From: birzanto [mailto:[EMAIL PROTECTED] Sent: Friday, October 08, 2004 11:01 AM To: [EMAIL PROTECTED] Subject: [Axapta-Knowledge-Village] Capacity Requirement Planning in Axapta Dear all, I would like to know where in Axapta can we calculate the rough capacity requirement (e.g. annual) based on forecast quantity that we want to produce, say in the next year. Can we get the total required time for Product X in Work Center C for example? And how to do the levelling if the required capacity is more than the capacity available? Thank you in advance. ------------------------ Yahoo! Groups Sponsor --------------------~--> $9.95 domain names from Yahoo!. Register anything. http://us.click.yahoo.com/J8kdrA/y20IAA/yQLSAA/kGEolB/TM --------------------------------------------------------------------~-> Sharing the knowledge on Axapta. Yahoo! Groups Links ------------------------ Yahoo! Groups Sponsor --------------------~--> Make a clean sweep of pop-up ads. Yahoo! Companion Toolbar. Now with Pop-Up Blocker. Get it for free! http://us.click.yahoo.com/L5YrjA/eSIIAA/yQLSAA/kGEolB/TM --------------------------------------------------------------------~-> Sharing the knowledge on Axapta. Yahoo! Groups Links <*> To visit your group on the web, go to: http://groups.yahoo.com/group/Axapta-Knowledge-Village/ <*> To unsubscribe from this group, send an email to: [EMAIL PROTECTED] <*> Your use of Yahoo! Groups is subject to: http://docs.yahoo.com/info/terms/