Hi All Master Planning Experts,
Help!Customer has the following scenario: Purchase Order delivery Lead times are very much longer then Sales Order delivery lead times. As such Purchase orders are created upfront in advance.For example a PO is created 12 months before receipt. To control the PO's,they set a 'Cancellation' period where these Purchase orders can be cancelled without them being liable for it.For example when a PO's delivery date falls between 5-6 months (cancellation period) from now,Master Planning should prompt them to take action on the PO. This would allow them to make changes to the PO while still in the 'Cancellation' period. Can Axapta handle this? Thanks in advance. Odin ------------------------ Yahoo! Groups Sponsor --------------------~--> In low income neighborhoods, 84% do not own computers. At Network for Good, help bridge the Digital Divide! http://us.click.yahoo.com/EpW3eD/3MnJAA/cosFAA/kGEolB/TM --------------------------------------------------------------------~-> Sharing the knowledge on Axapta. Yahoo! Groups Links <*> To visit your group on the web, go to: http://groups.yahoo.com/group/Axapta-Knowledge-Village/ <*> To unsubscribe from this group, send an email to: [EMAIL PROTECTED] <*> Your use of Yahoo! Groups is subject to: http://docs.yahoo.com/info/terms/