Hi Nilay

I agree with Andreas, this is the easiest workaround. Anything else will 
involve changing the scheduling code.

There are some issues with this solution especially if your costs, number of 
workers etc differ from shift to shift. But I would advice to bite the bullet 
(as far as possible) and not change the code.

Regards

Harry

________________________________
From: Axapta-Knowledge-Village@yahoogroups.com [mailto:[EMAIL PROTECTED] On 
Behalf Of andreas gunawan
Sent: 28 November 2006 14:34
To: Axapta-Knowledge-Village@yahoogroups.com
Subject: Re: [Axapta-Knowledge-Village] Re: Axapta Production Scheduling with 
Multiple Shifts...


Dear Nilay,
I've attached my answer about your question, maybe it wil be able to solve your 
question.
basically, I just create 2 shifts in calendar template and assign 24 hours 
calendar standard, by in working times composing windows I assign the template.


Rgds,


imaginationss <[EMAIL PROTECTED]<mailto:Nilay.Uygun%40tectura.com>> wrote:
Hi Harry,

I'm using Ax 3.0 with service pack 5
I hope we can find something for this because this is really a
critical issue for us right now.

thanks in advanve,
Nilay

--- In 
Axapta-Knowledge-Village@yahoogroups.com<mailto:Axapta-Knowledge-Village%40yahoogroups.com>,
 Harry Deshpande
<[EMAIL PROTECTED]> wrote:
>
> Hi NU
>
> I can understand what Ax is doing and it seems logical.
>
> What version are you using V3 or V4?
>
> Let me see if there is a workaround
>
> Regards
>
> Harry
>
>
> ________________________________
> From: 
> Axapta-Knowledge-Village@yahoogroups.com<mailto:Axapta-Knowledge-Village%40yahoogroups.com>
>  [mailto:Axapta-
[EMAIL PROTECTED]<mailto:Knowledge-Village%40yahoogroups.com>] On Behalf Of 
imaginationss
> Sent: 27 November 2006 12:59
> To: 
> Axapta-Knowledge-Village@yahoogroups.com<mailto:Axapta-Knowledge-Village%40yahoogroups.com>
> Subject: [Axapta-Knowledge-Village] Re: Axapta Production
Scheduling with Multiple Shifts...
>
>
> Hi,
>
> Could you please explain your answer to this question a bit more
> detailed for me?
>
> I'm having the same problem with the production scheduling and
> couldn't figure out how to solve it with the solution you mention.
>
> If we have a work center group (WCG) with 2 workers in it, working
> in shifts. Worker 1 (W1) is working between 08:00-14:00 and worker
2
> (W2) is working between 14:00-20:00.
> I assign the work to this WCG on the route.
> Let's say that the process time is 1 hours per product.
> I sell 9 items and run the master scheduling for "job scheduling" I
> will have 9 hours of workload in total. (1 hours per product X 9
> peaces)
> The system assigns the work to the W1 in the morning for 6 hours
> (between 08:00-14:00) and for the left 3 hours of work it waits
> until the next day 08:00 o'clock until the W1 becomes available
> again. The W2 sits free by this time without any workload. Normally
> we expect the system to assign the left 3 hours to the W2 to
> continue in the second shift. But it doesn't.
>
> This is really very critical for me right now.
>
> Thanks in advance
> NU
>
> --- In 
> Axapta-Knowledge-Village@yahoogroups.com<mailto:Axapta-Knowledge-Village%40yahoogroups.com><mailto:Axapta-
Knowledge-Village%40yahoogroups.com>, Michael Spadaro
> <mspadaro2@> wrote:
> >
> > Thanks Harry;
> >
> > That seems to be the way to work around this shortcoming in
Axapta.
> >
> > ms
> >
> > "Harry (Harshawardhan Deshpande" <harrydesh@> wrote:
> > hi
> >
> > Do you see any issue if you use a single work center with a
single
> calender (inclusive of multiple shifts)? (may be the number of
> workers differ from shift to shift?)
> >
> > regards
> >
> > harry
> >
> > mspadaro2 <mspadaro2@> wrote:
> > Hello All;
> >
> > In the plant where Axapta is used, there are 3 shifts - 1st, 2nd
> and
> > 3rd. We are trying to schedule people who assemble equipment. An
> > assembly operation usually takes more hours than can be
> accomplished
> > in a single shift. Therefore, people on the next shift take over
> > and continue assembling the equipment.
> >
> > I have a single work center group set up that contains individual
> > work centers. The work centers are of type 'Human Resource' and
> > represent each of the assembly people. I also have three
calendars
> > set up - one for each shift. The work centers contain the
> > appropriate calendar for the shift the person works.
> >
> > Whenever I run job scheduling for the production order it always
> > uses a single work center and schedules it out for multiple
> > consecutive days, scheduling only one shift per day. I want it to
> > schedule all three shifts in a single day - the first shift work
> > center, then the second shift work center, then the third shift
> work
> > center. After a single day of all three shifts having been
> > scheduled, then it should begin the process again for the next
day
> > until all of the demand is satisfied.
> >
> > In the route, I have set the 'Quantity of Work Centers' field to
3
> > and it still does not schedule consecutive shifts per day. In
> fact,
> > I get an interesting error.
> >
> > Any thoughts?
> >
> > Thanks in advance,
> >
> > Michael Spadaro
> > Clients First Business Solutions
> >
> >
> >
> >
> >
> > __________________________________________________
> > Do You Yahoo!?
> > Tired of spam? Yahoo! Mail has the best spam protection around
> > http://mail.yahoo.com
> >
> > Sharing the knowledge on Axapta.
> >
> >
> >
> >
> > SPONSORED LINKS
> > Business finance course Business to business finance Small
> business finance Business finance consultant Business finance
> magazine Business finance schools
> >
> > ---------------------------------
> > YAHOO! GROUPS LINKS
> >
> >
> > Visit your group "Axapta-Knowledge-Village" on the web.
> >
> > To unsubscribe from this group, send an email to:
> > Axapta-Knowledge-Village-
[EMAIL 
PROTECTED]<mailto:unsubscribe%40yahoogroups.com><mailto:Axapta-Knowledge-Village-
unsubscribe%40yahoogroups.com>
> >
> > Your use of Yahoo! Groups is subject to the Yahoo! Terms of
> Service.
> >
> >
> > ---------------------------------
> >
> >
> >
> >
> > ---------------------------------
> > Yahoo! for Good
> > Click here to donate to the Hurricane Katrina relief effort.
> >
>
>
>
> [Non-text portions of this message have been removed]
>

---------------------------------
Sponsored Link

$420,000 Mortgage for $1,399/month - Think You Pay Too Much For Your Mortgage? 
Find Out!

[Non-text portions of this message have been removed]



[Non-text portions of this message have been removed]

Reply via email to