Hi all We have some economic production quantity runs for our products. In order to plan the correct quantities, we use the min. order qty field under the quantity tab on the items form. Now a complication arise when we want to do transfers to our sales branches, using minimum/ safety stock levels for the branches. We setup branches to be refilled from our main distribution warehouse. When the MRP is run, the planned production order quantities refelct correct, but the planned transfers also takes the min. order qty into consideration - which we don't want becasue the safety levels on the branches is much lower than the econimic/min order qty for production.
Is there maybe anyone that can shed some light on how to approach this problem, i.e let planned transfer orders exclude minimum order quantity? Thanks Eddie