Hi All,
I want to split a Sales order for an Item of Bom type into Production orders 
based upon the capacity of the work centers assigned in the Route. For eg,
The work centers can produce 5 units per the work time assigned according to 
the calendar. If I raise a sale order for 10 units, the Production order needs 
to split into two production orders each of 5 units with different production 
order numbers. 
How can this Problem be addressed.
Regards,
Trinadh 