Hi Micheal,
 
The probelm is that i dont want to use the costing version , i want to get the 
price on the basis of Stock Model group in BOM Calculation.
 
Regards,
Hasan Bukhari


--- On Mon, 10/26/09, [email protected] <[email protected]> wrote:


From: [email protected] <[email protected]>
Subject: Re: [Axapta-Knowledge-Village] BOM Calculation Costing - Urgent
To: [email protected]
Date: Monday, October 26, 2009, 2:52 AM


  




Hi, 
 
try to set the fallback principle of the costing version to Active.
 
Best regards
Michael




From: S Hasan bukhari 
Sent: Saturday, October 24, 2009 1:18 PM
To: Axapta-Knowledge- vill...@yahoogro ups.com 
Subject: [Axapta-Knowledge- Village] BOM Calculation Costing - Urgent

  






Dear All,
 
The BOM Calculation picks the Items costs defined in the Costing Versions which 
is a standard cost. 
 
 
But i dont want to use the Cost Price based on the Stock Model not on the basis 
of Costing versions.if i have not defined the item cost price in Costing 
version , while running the BOM calculation AX is giving the message Cost Price 
is Zero.
 
 
Please reply as soon as possible
 
Regards,
Hasan Bukhari
















      

Reply via email to