Yes, Rufus....Continental received approval by MT Board of O & G Conservation for overlapping spacing units in September...Several other companies...XTO, Burlington..applied for the same overlapping units in the October meeting...approval pending....Picture it as follows: originally 2 section spacing..say 4 and 9...1280 acres...3 north-south 2 mile lateral wells have been drilled on 4 and 9...say one 1000 feet from the east lease line.....say one 1000 feet from the west lease line....and say one in the middle....those 3 wells were all part of the 4/9 1280 spacing...these overlapping spacings will run right on the east lease line and another on the west lease line...the first overlapping spacing will include 4/9/5/8--a 2560 acre spacing....the second overlapping spacing will include 4/9/3/10 a 2560 acre spacing.....so if I owned all of the minerals in 4 and 9, but none of the minerals in 5,8,3,10....I would have 3 "full" wells and 2 "half" wells if this makes sense.....Continental docketed 24 of these requests in the MT Sept meeting and XTO and Burlington another dozen or so for the Oct heading...so this is the wave coming next...Picture these two sections with five north and south laterals.....maybe someday, they will do east west laterals along the top and bottom lease lines and have different overlapping spacings with those sections....that is very possible down the road if these high density wells are paying off....In Elm Coulee now, many of the sections have 3 wells or about to get a 3rd well.......amazing...This density could carry over to Mountrail/Parshall in time, although it seems that most of those early wells are done diagonally accross the section, so it will look different...but still with higher density down the road.....after acreage is held by production and expiring leases are drilled. It will be interesting to watch how production is on these new overlapping wells...Perhaps this is all being done to set the table for carbon dioxide injection...Lot's of activity to watch!...Hope this answers your question, Rufus.....Steve
On Nov 3, 12:33 pm, "Rufus O'Malley" <[EMAIL PROTECTED]> wrote: > I recently read that in Montana there has been some activity with > merging 2, and even 3 1280-acre spacing units to create mega-spacing > units with entirely new well density allowances.... I can't seem to > backtrack to the article to post it, but the gist of it was that once > a 1280 had hit it's max density, that it merges with an adjacent 1280 > to create a 2560 or merges 3 separate 1280's to create a 3840-acre > unit where addt wells with different orientations are being allowed. > Anybody hear anything else about this? If this IS being done, it > brings me to the following question: > How many spacing units can an individual section,or portion thereof, > be part of? > For example: let's take a section 4 over 9 standup - can section 4 > concommitantly be in a section 5 and 4 laydown unit? And then again, > into a 4-3 laydown unit at the same time... ?? > Rufus --~--~---------~--~----~------------~-------~--~----~ You received this message because you are subscribed to the Google Groups "Bakken Shale Discussion" group. To post to this group, send email to [email protected] To unsubscribe from this group, send email to [EMAIL PROTECTED] For more options, visit this group at http://groups.google.com/group/bakken-shale-discussion?hl=en -~----------~----~----~----~------~----~------~--~---