On Wed, Sep 15, 2021 at 4:16 PM Yoav Weiss <[email protected]> wrote:

>
>
> On Wed, Sep 15, 2021 at 9:40 PM Patrick Meenan <[email protected]>
> wrote:
>
>>
>>
>>
>>>
>>>>
>>>> Estimated milestones
>>>> OriginTrial desktop last 101
>>>> OriginTrial desktop first 96
>>>> OriginTrial android last 101
>>>> OriginTrial android first 96
>>>>
>>>
>>> Any particular reason you want to run the OT for 6 milestones?  It may
>>> be better to start with 4 and extend as needed..
>>> Do you have partners lined up to experiment?
>>>
>>
>> Moving to a 4-week release cycle, calendar-wise it's about the same.
>> Optimally we will be able to make the ship decision within a couple of
>> weeks of hitting stable but in case the process takes longer than expected
>> I was erring on the side of a bit of buffer so it doesn't get disabled from
>> under a site as we work to ship. There's also the potential for some
>> delayed feedback cycles as the LCP impacts and side-effects will be
>> measured through RUM tools and search console's 28-day rolling average on
>> CrUX data.
>>
>> Is there a problem with planning for a bit of a buffer and ending sooner
>> rather than planning sooner then scrambling to extend?
>>
>
> Before the move to 4 weeks per milestone, a typical was run for 2-3
> milestones, which is equivalent to 3-4.5 nowadays. Let's settle on 5
> milestones? :)
>
> Extending the trial if needed shouldn't take more than sending an intent
> to extend, ideally with learnings so far.
>


SGTM. I'd like to ship as soon as possible anyway and have no interest in
dragging it out.

-- 
You received this message because you are subscribed to the Google Groups 
"blink-dev" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To view this discussion on the web visit 
https://groups.google.com/a/chromium.org/d/msgid/blink-dev/CAPq58w4v%2BYnLgUHkoYejeWkcpd0NwnVHKo125DjL9dARk3MVxg%40mail.gmail.com.

Reply via email to