Hello, I confirmed this bug into web-client. expected date of the PO is a function field which are calculated base on scheduling date of PO lines. After change of Schedule date of any PO line, expected date of PO is not updated. Web client is sent request to call calculation of expected date but On Save, web client is not consider this new expected date.
Thanks -- You received this bug notification because you are a member of C2C OERPScenario, which is subscribed to the OpenERP Project Group. https://bugs.launchpad.net/bugs/696793 Title: [6.0] Purchase expected date wrong value Status in OpenObject Web Client: Confirmed Bug description: Create a purchase order, create two lines with two different products and don't define an expected date on the PO. 1st line : Scheduled date = 01/23/2011 2nd line : Scheduled date = 01/13/2011 If you save the PO, the expected date of the PO is today and the scheduled date of two lines is also today whereas it should be 01/13/2011. After that, if you remove the expected date on the PO, change the scheduled date on lines with the value defined above and save the PO, values are ok. Values should be ok at the first saving time. _______________________________________________ Mailing list: https://launchpad.net/~c2c-oerpscenario Post to : [email protected] Unsubscribe : https://launchpad.net/~c2c-oerpscenario More help : https://help.launchpad.net/ListHelp