Hi all,
I've attached the current GUI status. We can discuss further at the
meeting.
Thanks,
Niall.
On Mon, 2007-03-26 at 16:34 -0600, Sarah Jelinek wrote:
> Details:
>
> Tuesday 3/27/07 @ 9am PT/10am MT/11am CT/noon ET/5pm Prague/Midnight Beijing
>
> Toll Free Dial In Number: (866)545-5227
> Int'l Access/Caller Paid Dial In Number: (865)673-6950
> ACCESS CODE: 1337371#
>
> Agenda:
> -Design doc reviews
> -Status from sub-projects
> -GUI
> -Target discovery
> -Orchestrator
> -Schedule tracking updates(Sarah)
> -Open
>
> sarah
-------------- next part --------------
Layout template (Niall): Done
- after much fiddling with the precious branding.
language pre-install (Jedy): 95%
- Language list is hardcoded. If that's ok
then it's done, otherwise need an API.
keyboard pre-install (Jedy): 90%
- needs orchestrator API for completion
Welcome screen (Niall): 95%
- Needs to read in release notes from file.
Disk Partitioning screen (Niall): 25%
- Widget Layout complete.
- Working on UI logic
- Dependent on orchestrator for disk data,
using dummy data at the moment.
Upgdrade Environment (Jedy): 0%
- Awaiting final UI spec before work can
begin
Date, time & Timezone: (Niall/Jedy) 40%
- Layout complete
- Date + time functionality working.
- Jedy will work on timezone functionality
while Upgrade screen UI spec is pending.
Language Support: (Jedy): 80%
- UI complete mostly.
- Some minor UI logic remaining.
- Needs API from orchestrator for completion
Password & Users: (Matt) 95%
- Functionally complete
- Needs orchestrator API for completion
Summary/Confirmation (Matt): 65%
- Layout complete
- UI complete except displaying license agreement
- Needs selection data from all screens for completion
- Needs orchestrator API to build install profile
Installation Progress: (Matt): 0%
Installation Failure: (Matt or Jedy) 0%
Issues
---------
- Spent a lot of time discussing visual specification and related issues -
hopefully resolved now.