Hi,

ESB:

Stub Separation : Done for some components. All the mediators and some other
ESB components are yet to be completed.
Integration Test : Endpoint tests were completed. Working on mediators
tests.
Bug Fixing : Will start working on L1s, once we finish stub separation.
No any blocking issues.

Thanks.
On Tue, Mar 22, 2011 at 11:21 AM, Dinithi Nallaperuma <dini...@wso2.com>wrote:

>
> Hi,
>
> GS progress update as below.
>
> *Stub Separation*
>
> Started the task and have completed for one component.
>
> *Integration Tests*
>
> Almost done with the task. Will be done by the EOD.
>
> *Bug Fixing*
> Fixing of L1 and L2 bugs - 50% done. This is carried out in between the
> stub separation and integration test tasks.
>
>
> No blocking issues so far. Will update the status.
>
> Thank you
> Regards,
> Dinithi Nallaperuma
>
>
>
>
> _______________________________________________
> Carbon-dev mailing list
> Carbon-dev@wso2.org
> http://mail.wso2.org/cgi-bin/mailman/listinfo/carbon-dev
>
>


-- 
Kasun Indrasiri
Senior Software Engineer
WSO2, Inc.; http://wso2.com
lean.enterprise.middleware

cell: +94 71 536 4128
Blog : http://kasunpanorama.blogspot.com/
_______________________________________________
Carbon-dev mailing list
Carbon-dev@wso2.org
http://mail.wso2.org/cgi-bin/mailman/listinfo/carbon-dev

Reply via email to