As long as "go back to #3" means feature-freeze-bug-squashing, it sounds
like a good plan.  You could iterate on additional RCs quicker depending on
the open issue(s) and dev availability.


On Tue, Dec 22, 2015 at 1:53 AM, Misagh Moayyed <[email protected]> wrote:

> Fellow Devs,
>
>
>
> Thought I provide a quick status update on the 4.2 dev line prior to the
> nearing release candidate:
>
>
>
> 1.       63 issues closed, 111 pull requests closed since Sep 19 2015.
>
> 2.       Tentative RC1 release date is Sunday Dec 27.
>
> a.       3-month iteration for a minor release.
>
> b.       This may have to be delayed by a couple of days to finalize 1-2
> pending issues but so far, it seems like we are on schedule.
>
> 3.       Wait about 4 weeks after RC1 to cut the next release, whether
> that would be the GA or RC2. If GA, stop. Else, go back to #3
>
> 4.       Moving towards 4.3. Roadmap outlined on the wiki.
>
>
>
> All agreeable?
>
>
>
> Misagh
>
> --
> You received this message because you are subscribed to the Google Groups
> "CAS Developer" group.
> To unsubscribe from this group and stop receiving emails from it, send an
> email to [email protected].
> Visit this group at https://groups.google.com/a/apereo.org/group/cas-dev/.
>

-- 
You received this message because you are subscribed to the Google Groups "CAS 
Developer" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
Visit this group at https://groups.google.com/a/apereo.org/group/cas-dev/.

Reply via email to