Good to hear, Arun.  Smart move not changing your addressing scheme during
the move, now you have plenty of time to work out a migration strategy that
won't put your sites and users at risk (priority 1).

On Sun, Oct 18, 2009 at 1:16 AM, Arun Kumar <[email protected]> wrote:

> Hi All,
>
> Just to give you all an update on this:
>
> With everyone's valuable info and other info, migrated whole setup of IP
> Telephony (6 Servers + 3 VG Transcoders + Couples of GW MGCP / H323) to new
> site and downtime was very less 15-20 min.
>
> In new site I kept the same subnet and ip addressing scheme as earlier so
> it made my life really easy and yesterday completed this whole migration and
> everything is seems to be working fine.
>
> So again thanks very much everyone for your valuable feedback and
> suggestion.
>
> Thanks
> Arun
>
>
>
> On Thu, Sep 24, 2009 at 5:55 AM, Michael Ciarfello <[email protected]
> > wrote:
>
>>  IPCC SRND.  4.5, but it hasn't changed.  See page 3.1 for the IPCC / CTI
>> requirement.
>>
>> http://www.cisco.com/en/US/docs/voice_ip_comm/cust_contact/contact_center/crs/express_4_5/srnd/crs4.5srnd.pdf
>>
>> Other than that, change the JTAPI and RMJTapi groups so that the primary
>> CTI server ponts to the CCM server that is moved and were you will move the
>> IPCC server to.  You may have to change the device pool all the CTI ports
>> are pointing to so that the CallManager group has listed first the CCM
>> server that already moved.  You might want to create a new DP that has only
>> the CCM that already moved.  You don't want it (CTI / JTAPI / RMJTAPI)
>> failing over to the distant CCM server.
>>
>> I think that's it.  Let me (us) know if you have additional questions.
>>
>>
>>  ------------------------------
>>  *From:* Arun Kumar [[email protected]]
>> *Sent:* Wednesday, September 23, 2009 10:42 AM
>>
>> *To:* Michael Ciarfello
>> *Cc:* Nara Shikamaru; [email protected]
>> *Subject:* Re: [OSL | CCIE_Voice] Moving IP Telephony Setup
>>
>>   Hi Michael,
>>
>> Can you please provide me any link what re-configuration I need to do in
>> IPCC to make the setup successful.
>>
>> Thanks
>> Arun
>>
>>
>> On Wed, Sep 23, 2009 at 7:23 PM, Michael Ciarfello <
>> [email protected]> wrote:
>>
>>>  IPCC must be co-located on the same LAN (simplicity.  Read the IPCC
>>> SRND for full details, I think 45MB would be enough) as the CTI server it
>>> connectes to.  SO move the IPCC and reconfig if necessary to connect it to
>>> the CCM that moved.
>>>  ------------------------------
>>>  *From:* Arun Kumar [[email protected]]
>>> *Sent:* Wednesday, September 23, 2009 7:46 AM
>>> *To:* Nara Shikamaru
>>> *Cc:* Michael Ciarfello; [email protected]
>>>
>>> *Subject:* Re: [OSL | CCIE_Voice] Moving IP Telephony Setup
>>>
>>>   Hi All,
>>>
>>> I've started my move and so far moved successfully, one Unity 5 and CCM 5
>>> but I've to move my IPCC Servers also (version 5) and IP's are changed now.
>>> I've moved Unity and CCM and tested with New IP Changes works fine but I'm
>>> not sure on IPCC Move, what needs to be done on IPCC Servers, CCM Side ? so
>>> if anyone can give some guidance or link to some doc on this will be really
>>> helpful as without this I'll not be able to move my CCM PUB.
>>>
>>> Thanks for you all your valuable suggestions.
>>>
>>> Regards
>>> Arun
>>>
>>>
>>>
>>> On Tue, Sep 15, 2009 at 11:32 AM, Arun Kumar <[email protected]> wrote:
>>>
>>>> Nara thanks very much I'll surely take these things into the
>>>> consideration before going for any move.
>>>>
>>>> Cheers
>>>>
>>>>
>>>> On Tue, Sep 15, 2009 at 11:14 AM, Nara Shikamaru <[email protected]
>>>> > wrote:
>>>>
>>>>> I would register the phones and gateways at both sites to a single
>>>>> host, move the free host to the new site, move its phones and gateway to 
>>>>> the
>>>>> new site and have them register to it (at this point, only site-to-site
>>>>> dialing and voicemail will be down.), then move the other host and its
>>>>> phones/gateway to the new site.  Anyway, there are a dozen ways to do it 
>>>>> and
>>>>> all of them involve some kind of outage.  Don't get tricky and try to 
>>>>> change
>>>>> IP addresses between the old and new sites and you'll be fine - move your
>>>>> phone network and get it up and operational so that the sites have
>>>>> telephony.  If you work with someone who knows everything and starts
>>>>> insisting that the subnets need to be changed at the new sites, tell them 
>>>>> to
>>>>> recreate the subnets only for telephony and you can work on changing the
>>>>> voice network addressing scheme some other time.  99.99 percent of the 
>>>>> time
>>>>> moves like these turn into disasters when the engineer decide to get fancy
>>>>> at the wrong time.  Keep it simple.
>>>>>
>>>>> And no, do NOT "rebuild the cluster".  Shut hosts down gracefully, move
>>>>> them, and make sure the new sites can ping each other when you put the 
>>>>> hosts
>>>>> in the new networks.
>>>>>
>>>>>
>>>>> On Mon, Sep 14, 2009 at 9:23 PM, Michael Ciarfello <
>>>>> [email protected]> wrote:
>>>>>
>>>>>>  Yea, that works.  You don't even have to stop the servivces, just
>>>>>> shut down the server and move it.
>>>>>>
>>>>>> It's up to you if you want to change the CallManager group to
>>>>>> gracefully re-register the phones and gateways to the PUB before turning 
>>>>>> the
>>>>>> SUB off.
>>>>>> If you have H323 gateways, you might want to test if they are still
>>>>>> taking calls (you have preference command to both CCM's, the voice class
>>>>>> h323 command is working properly, etc.
>>>>>>
>>>>>> When it's time to move the PUB, you might want to make sure you take a
>>>>>> COUPLE of bars backups in case something gets damaged.
>>>>>>
>>>>>> You should have a testing plan and run through it after you turn the
>>>>>> SUB off and before you take it away.
>>>>>>  ------------------------------
>>>>>> *From:* Arun Kumar [[email protected]]
>>>>>> *Sent:* Tuesday, September 15, 2009 12:16 AM
>>>>>> *To:* Michael Ciarfello
>>>>>> *Cc:* Nara Shikamaru; [email protected]
>>>>>>
>>>>>> *Subject:* Re: [OSL | CCIE_Voice] Moving IP Telephony Setup
>>>>>>
>>>>>>   thanks, I'll take care of this valuable information but for my
>>>>>> setup do I really need to break the cluster ? I'm thinking just stop all 
>>>>>> the
>>>>>> services on SUB and then take the SUB offline and move to new office and
>>>>>> connect in same LAN as both office's are connected and have IP Addressing
>>>>>> scheme. Once SUB is offline take the PUB offline (during off hours, so my
>>>>>> SUB will be able to handle that call volume) and move to new location.
>>>>>>
>>>>>> thanks
>>>>>>
>>>>>> On Tue, Sep 15, 2009 at 9:31 AM, Michael Ciarfello <
>>>>>> [email protected]> wrote:
>>>>>>
>>>>>>>  Don't forget that when the PUB is down, people won't get
>>>>>>> user-facing features such as MWI, call forward all, etc.
>>>>>>>  That functionality doesn't start until 6.1.  Call Forward all might
>>>>>>> be required for a receptionist who call forwards to a Unity CallHandler 
>>>>>>> for
>>>>>>> after hours support, etc.  You can probably wait until after hours, 
>>>>>>> then do
>>>>>>> a BAT export, then look through the CSV file in a spreadsheet program 
>>>>>>> and
>>>>>>> see who has call forward all set.
>>>>>>>
>>>>>>> You stated you didn't have CTI dependent applications such as IPCC.
>>>>>>> That's good becasue of the very-low round trip time dependency.  The 
>>>>>>> IPCC
>>>>>>> pepople would also require the PUBlisher to login and change state.
>>>>>>>
>>>>>>> If Unity is UM.  Make sure your Unity and Exchange move according to
>>>>>>> the Unity Design document.  Those have to be on the same 100Mb LAN 
>>>>>>> usually
>>>>>>> with AD and Domains and Global Catalog positioning properly, otherwise 
>>>>>>> you
>>>>>>> will get weird Unity issues.  Your MS people might want to move the 
>>>>>>> users to
>>>>>>> a mailstore at the new location where the new Unity server will be 
>>>>>>> placed.
>>>>>>>
>>>>>>> To break the cluster, you will have to delete all the dependent
>>>>>>> objects in CCMAdmin then finally delete the system-> server object.  
>>>>>>> Don't
>>>>>>> know if that's all required.  You will have to change the IPAddress 
>>>>>>> when you
>>>>>>> move it to your new location.  CallManager 5.x had a BUNCH of database 
>>>>>>> sync
>>>>>>> issues.  I've had TAC in the Linux shell performing database commands 
>>>>>>> once.
>>>>>>> Another engineer for another customer spent Thanksgiving holiday (and a
>>>>>>> couple other night downtimes) at a customer site fighting through 
>>>>>>> database
>>>>>>> issues.  Might want to upgrade to at least 6.1 first.
>>>>>>>
>>>>>>>
>>>>>>>  ------------------------------
>>>>>>> *From:* [email protected] [
>>>>>>> [email protected]] On Behalf Of Arun Kumar [
>>>>>>> [email protected]]
>>>>>>> *Sent:* Monday, September 14, 2009 10:55 PM
>>>>>>> *To:* Nara Shikamaru
>>>>>>> *Cc:* [email protected]
>>>>>>> *Subject:* Re: [OSL | CCIE_Voice] Moving IP Telephony Setup
>>>>>>>
>>>>>>>   Hi Nara,
>>>>>>>
>>>>>>> Thanks for your input. I'm thinking to just stop the SUB (All
>>>>>>> Services and then shutdown the system) and then move the SUB to another
>>>>>>> office (let me know if any better way to do this ? or how can I break 
>>>>>>> the
>>>>>>> Cluster ?). Plug back SUB and will make sure PUB is reachable then will 
>>>>>>> do
>>>>>>> the same with PUB. Later I'll move my Unity.
>>>>>>>
>>>>>>> Please let me know your thoughts on this or any better way to do
>>>>>>> this.
>>>>>>>
>>>>>>> Thanks
>>>>>>> Arun
>>>>>>>
>>>>>>> On Tue, Sep 15, 2009 at 4:30 AM, Nara Shikamaru <
>>>>>>> [email protected]> wrote:
>>>>>>>
>>>>>>>> Arun,
>>>>>>>>      What do you mean by "rebuild the cluster"?  If you have a pub
>>>>>>>> at one site and a sub at the other, you probably have each site's phone
>>>>>>>> register locally to their own host (eliminating the need for SRST for 
>>>>>>>> the
>>>>>>>> most part.)  The only thing that's affected when you move the hosts is
>>>>>>>> intrasite dialing between the two buildings and voicemail/call 
>>>>>>>> handlers will
>>>>>>>> be unavailable.  This is pretty much a matter of making sure that the 
>>>>>>>> IP
>>>>>>>> schemes are not changed at each new site so that you don't have to go
>>>>>>>> through anything like change IP addresses on CUCM and Unity - which 
>>>>>>>> can be
>>>>>>>> done but is something that I would stay from when time is short in a 
>>>>>>>> move
>>>>>>>> like this.  Just recreate your subnets and VLANs, make sure both sites 
>>>>>>>> can
>>>>>>>> talk to each other, then move your equipment.
>>>>>>>>
>>>>>>>>      When you port your new numbers to the new circuits, hopefully
>>>>>>>> you're going to be staying with the same carrier and that they're 
>>>>>>>> aware that
>>>>>>>> time is of the essense once your voice gateway at the new site is up.
>>>>>>>>
>>>>>>>>   On Mon, Sep 14, 2009 at 11:31 AM, Arun Kumar 
>>>>>>>> <[email protected]>wrote:
>>>>>>>>
>>>>>>>>>  Hi All,
>>>>>>>>>
>>>>>>>>> I know this may be not the right place but I know here are many
>>>>>>>>> experts so please provide your valuable feedback:
>>>>>>>>>
>>>>>>>>> My HQ Setup:
>>>>>>>>>
>>>>>>>>> 1. One Cisco 3825 Voice Gateway
>>>>>>>>> 2. Two CCM 5.x Servers
>>>>>>>>> 3. 1 Unity 5.x
>>>>>>>>>
>>>>>>>>> we're shifting the office and assigned the task to move the IP
>>>>>>>>> Telephony to other office( both the office's are connected via MPLS 
>>>>>>>>> 10 MB
>>>>>>>>> Links) with *Zero downtime*. Please let me know how can I go about
>>>>>>>>> it ?
>>>>>>>>>
>>>>>>>>> This is what I thought:
>>>>>>>>>
>>>>>>>>> 1. Break the CCM Cluster and move Subscriber to other office
>>>>>>>>> 2. Configure Cluster over the WAN again
>>>>>>>>> 3. Break the Cluster again and Move the PUB to new office and
>>>>>>>>> rebuild the cluster
>>>>>>>>> 4. Move the Unity Server ( I don't think I can have Zero downtime)
>>>>>>>>> 5. Got New Line with same DID range in new office (not operational
>>>>>>>>> yet)
>>>>>>>>> 6. Configure other 3825 VG and make it Live and take the Original
>>>>>>>>> VG Down
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> please provide your valuable suggestion on moving this ? Please let
>>>>>>>>> me know if you need any other info.
>>>>>>>>>
>>>>>>>>> Cheers
>>>>>>>>> Arun
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> _______________________________________________
>>>>>>>>> For more information regarding industry leading CCIE Lab training,
>>>>>>>>> please visit www.ipexpert.com
>>>>>>>>>
>>>>>>>>>
>>>>>>>>
>>>>>>>>
>>>>>>>> --
>>>>>>>> -Shikamaru
>>>>>>>>
>>>>>>>
>>>>>>>
>>>>>>
>>>>>
>>>>>
>>>>> --
>>>>> -Shikamaru
>>>>>
>>>>
>>>>
>>>
>>
>


-- 
-Shikamaru