If you schedule them for same time, they will both fire off at the same time
- can your script handle two simultaneous calls?
We have four instances and a task we want run every 15 minutes
So instance 1 runs at 00
instance 2 runs at 15
instance 3 runs at 30
instance 4 runs at 45
Think of each instance as a separate CF server
Even though they may share the same code
they each have their own APPLICATION scope
On Fri, Apr 11, 2008 at 2:32 PM, George Lu <[EMAIL PROTECTED]> wrote:
> I've got two instances (instance1 & 2) in a cluster on a CF8 server. My
> question is should I enable schedule tasks in both instances or just one of
> instances?
>
> Regards,
> George
>
> >
>
--