I just received from Steve further details of the manufacturing process we have planned. I quote:


Bringing a product to mass production goes through several steps. For
Freerunner, since we intend it to be usable by the mass market, we are being very diligent.


Here are the milestones:

Design Verification Testing (DVT)
---------------------------------
A 100 or so phones have been built for design verification testing. These are based on A5. These phones are ready to enter testing. This testing will include:

  FUNCTIONAL TESTING
  PERFORMANCE TESTING
  COMPLIANCE ( like FCC and CE)
  CLIMATIC TESTING


When DVT is completed successfully to the satisfaction of all parties involved, we start PVT:


Pilot Verification Test (PVT)
-----------------------------
PVT is staged to go. This means we have the parts in the factory ready to do the build and we are analyzing the results of DVT. In PVT we are looking to perfect the design for production so that we get a good yield when we decide to build a million phones.

The PVT runs are staggered: for example, we may build 100 phones and test them, then make a minor change and build another 100, tweak again and then perhaps build 200. Repeat until we verify that the product is ready for true mass production.


Steve explicitly says:

"If the community would like, I will update them on each and every stage.

(I've already answered yes for all of you :-)

Michael