Hi,
I will take a moment before Wednesday for the BPEL and SCA contributions.
Right now, I have a Git issue with BPEL. This is in the hands of the
webmaster now.
Vincent.
Le 09/11/2012 01:57, David M Williams a écrit :
Still several "previous contributions" that have not been re-enabled ....
emf-query2.b3aggrcon - org.eclipse.simrel.build
gyrex.b3aggrcon - org.eclipse.simrel.build
jwt.b3aggrcon - org.eclipse.simrel.build
mylyn-docs-intent.b3aggrcon - org.eclipse.simrel.build
soa-bpel.b3aggrcon - org.eclipse.simrel.build
soa-sca.b3aggrcon - org.eclipse.simrel.build
And a number of additional ones that contain disabled repos for
features ... some of which may be waiting on the above contributions?
amp.b3aggrcon - org.eclipse.simrel.build
dltk.b3aggrcon - org.eclipse.simrel.build (2 matches)
egit.b3aggrcon - org.eclipse.simrel.build
emf-emf.b3aggrcon - org.eclipse.simrel.build
mylyn.b3aggrcon - org.eclipse.simrel.build (2 matches)
tcf.b3aggrcon - org.eclipse.simrel.build (2 matches)
tm.b3aggrcon - org.eclipse.simrel.build
webtools.b3aggrcon - org.eclipse.simrel.build
Let me know if I can help.
And I'll give an early reminder that the next cycle (M4) will be a
little shorter for some (most) projects since we shift to the "one
week" window then,
From
http://wiki.eclipse.org/Kepler/Simultaneous_Release_Plan#Schedule
Elapsed Weeks
End Date Span from +0 for RC0 for EPP avail
M1 Friday, August 24, 2012 08/10 to 08/24 6 8
(from previous release GA)
M2 Friday, October 05 09/21 to 10/05 6 6 (from M1)
M3 Friday, November 16 11/02 to 11/16 6 6 (from M2)
M4 Friday, December 21 12/14 to 12/21 6 5 (from M3)
(shift from 2 week window to 1 week window)
Thanks!
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@eclipse.org
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@eclipse.org
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev