Hi,
Since the last post of this email, it looks like many tasks under
milestone 1 group are completed or being worked on. Can everyone update
JIRA tasks and close the tasks if you think they are done? Then I can go
through the JIRA tasks and see where we are at for the first milestone
release.
Dan probably is right about aggressiveness of releasing something before
ApacheCon, but we certainly can re-assess JIRA tasks after everyone's
update and see when it is a feasible date for the first milestone.
Cheers,
Bo
Dan Diephouse wrote:
One week before ApacehCon might be slightly agressive, but we can shoot
for it.
Regarding the wiki page, thigns look fine for the most part, but I don't
think WS-RM will be ready. Also, I'd appreciate it if you could see if
anything on that list isn't in jira, and if its not, update it and
schedule the issues for milestone 1. :-)
- Dan
Bozhong Lin wrote:
Hi All,
As CeltiXfire merged code is getting more stable everyday, and people
are working hard to port the old Celtix/Xfire features to new
CeltiXfire architecture, it may be a good time now to consider the
timing of CeltiXfire milestone 1 release. Since ApacheCon US is
happening on Oct. 9, one week before ApacheCon US sounds to be a good
timing for CeltiXfire milestone. Getting out a stable kit at ApacheCon
US sounds exciting to me. What do people think?
I started a wiki page [1] to collect some of features that folks are
working on and might be good candidates for milestone 1 release
features. Please feel free to add any missing features.
Thanks,
Bo
[1] http://cwiki.apache.org/confluence/display/CXF/Milestone+1+Plan