Hi Jonathan,

On Thu, Jun 20, 2024 at 10:35:35PM +0100, Jonathan Wiltshire wrote:
> Hi,
> 
> A finally-final point release is required for bullseye, and we're a bit
> constrained on dates. The security team (CC) wish to cease security support
> from Wednesday 14th August and hand over to LTS as soon as a wash-up release
> can be organised.
> 
> The weekend of 24th August is unworkable. That leaves two options:
> 
>  - Saturday 17th August: this would mean freezing on the 10th, before
>    security support ends, so the security team's cooperation in keeping
>    non-critical DSAs off the table during the freeze period would be
>    required

Sure, you will have our full cooperation; this will be fine from our
side and keeping non-critical DSAs off the table as needed.

Rgards,
Salvatore

Reply via email to