Hi, Use of buster-security will pass from the Security Team to LTS in a few days time, so we should get the EOL point release organised. We need at least a couple of weeks to get things sorted, so as some suggestions:
- August 20 - [August 27 doesn't work for at least me and the Images Team, so nope] - September 3rd - September 10th We're currently only 3 weeks past the 11.4 bullseye point release, but that was also about 6 weeks late. It's therefore worth considering whether we want to try and get 11.5 out sooner and get back onto the previous track, or delay it a little more and aim for every two months from 11.4's release date. tl;dr - please indicate your availability / preferences for the above dates (for both 10.13 and 11.5) and any opinions on whether we should do them at the same time or separately. Thanks, Adam