> Hello everyone!
> 
> As per the previously agreed-upon schedule for Beam releases, the
> process for the 2.6.0 Beam release should start on July 17th.
> 
> I volunteer to perform this release. 
> 
> Here is the schedule that I have in mind:
> 
> - We start triaging JIRA issues this week.
> - I will cut a release branch on July 17.
> - After July 17, any blockers will need to be cherry-picked into the
> release branch.
> - As soon as tests look good, and blockers have been addressed, I will
> perform the other release tasks.
> 
> Does that seem reasonable to the community?
> 