Hi Next month (december) we should aim to get a new 3.7 LTS release out.
So lets start to close down on remaining work, and get CI stable. I am currently working on compiled simple language (preview) for 3.7 which is an effort that takes all of this week. The JIRA has 43 tickets assigned https://issues.apache.org/jira/issues/?jql=project%20%3D%20CAMEL%20AND%20fixVersion%20%3D%203.7.0%20AND%20statusCategory%20%3D%20new Some of those can likely be moved to 3.8, as usual we dont have time to complete all those tickets. Lets try to take 2 weeks of development and then see if we are ready for cutting the RC. -- Claus Ibsen ----------------- http://davsclaus.com @davsclaus Camel in Action 2: https://www.manning.com/ibsen2