What I mean is that to prevent the date of oct '14 moving we need to
move the feature freeze forward. so we have more time to create the
release.

On Tue, May 27, 2014 at 10:45 PM, Ritu Sabharwal <rsabh...@brocade.com> wrote:
> When  you say release schedule shift, does it mean 4.5 release target is 
> moved from Oct '14 to a forward date?
>
> Thanks & Regards,
> Ritu S.
>
> -----Original Message-----
> From: Daan Hoogland [mailto:daan.hoogl...@gmail.com]
> Sent: Monday, May 26, 2014 5:26 AM
> To: dev
> Subject: [ACS45][ACS50][PROPOSAL] move forward feature freeze
>
> LS,
>
> When I seeing once again our release schedule shift, I think we have no 
> option but to move feature freeze for the next release forward.
> This is the only way it seems we can reduce the complexity of the total sum 
> of changes. Therefore it is the only way we can prevent lapsing even more in 
> time without risking reduced quality of our next release.
> So I propose to move feature freeze forward by a month to be at the 19th of 
> June (instead of July). I don't think we need to strictly move code freeze 
> forward as well but vigilance onto added features will be necessary.
>
> --
> Daan



-- 
Daan