+1 for moving directly to 0.10.

2015-09-29 11:40 GMT+02:00 Maximilian Michels <m...@apache.org>:

> Hi Kostas,
>
> I think it makes sense to cancel the proposed 0.10-milestone release.
> We are not far away from completing all essential features of the 0.10
> release. After we manage to complete those, we can test and release
> 0.10.
>
> The 0.10 release will be a major step towards the 1.0 release and,
> therefore, all new features of 0.10 should get enough exposure until
> we release 1.0.
>
> Cheers,
> Max
>
> On Tue, Sep 29, 2015 at 11:26 AM, Kostas Tzoumas <ktzou...@apache.org>
> wrote:
> > Hi everyone,
> >
> > I would like to propose to cancel the 0.10-milestone release and go
> > directly for a 0.10 release as soon as possible.
> >
> > My opinion would be to focus this release on:
> > - Graduating the streaming API out of staging (depends on some open pull
> > requests)
> > - Master high availability
> > - New monitoring framework
> > - Graduating Gelly out of staging
> >
> > Flink 1.0 will probably come after 0.10, which gives us time to fix open
> > issues and freeze APIs.
> >
> > What do you think?
> >
> > Best,
> > Kostas
>

Reply via email to