Mikhail Loenko wrote: > I've added new requirements from this thread to [1,2] > > I've also put names of the requirements. > We may use these names in comments to JIRAs to simplify search. > > Please comment > > Thanks, > Mikhail > > [1] http://harmony.apache.org/m2.html > [2] http://svn.apache.org/viewvc/harmony/standard/site/docs/m2.html?view=co
I have a problem with the way the requirements are being stated for M2. Maybe it is just the terminology I'm uncomfortable with, that they are being stated as 'requirements' and not 'goals'. What happens if these requirements are not met? Do you slip the date of M2 or drop some requirements? I would suggest that instead we have timeboxed stable development cycles, and plan what should get into each stable milestone. I still haven't heard a good reason why these should be put into JIRA titles either. Can't we just agree that a JIRA should be in Milestone 'X' or not? Are you looking to group the JIRA issues into themes? Regards, Tim