Sean,

Do you have a target date you'd like to see the community aiming for on
this one?

If you don't mind, I would propose the Release Wrangler get started in JIRA
pruning and test suite kicking over the next couple weeks, and we can
target the first or second week of Dec. There's been quite a few commits
since the last release, so there may be some surprises lurking for our
volunteers to sort out. A good place to start is the compatibility report.

Who will carry this banner? Apekshit, Jan: shall we draw straws? One of you
have a bit of extra free time over the next 4 weeks?

Thanks,
Nick

On Wed, Nov 1, 2017 at 11:33 AM Jan Hentschel <
jan.hentsc...@ultratendency.com> wrote:

> I also like to volunteer, but I don’t think that I can do it on my own.
>
>
>
> Jan
>
>
>
> From: Apekshit Sharma <a...@cloudera.com>
> Reply-To: <dev@hbase.apache.org>
> Date: Wednesday, November 1, 2017 at 12:24 AM
> To: <dev@hbase.apache.org>
> Subject: Re: [DISCUSS] Any committers willing to do maintenance releases
> over the holidays?
>
>
>
> Loads of helping hands...woohoo!
>
>
>
> -Appy
>
>
>
>
>
> On Oct 31, 2017 4:01 PM, "Nick Dimiduk" <ndimi...@gmail.com> wrote:
>
>
>
> As 1.1 is rounding down, I will be able to apply that time to helping out
>
> on another release line, if that's useful to the community.
>
>
>
> Thanks,
>
> Nick
>
>
>
> On Mon, Oct 30, 2017 at 9:35 PM, Sean Busbey <bus...@apache.org> wrote:
>
>
>
> > Hi folks!
>
> >
>
> > I'm in the process of getting us a 1.2.7-RC, hopefully soon[1]. This
>
> > release is badly behind schedule. I'd very much like to get us back on
>
> > a regular cadence for our stable release line, with a goal of once a
>
> > month. Unfortunately, I'm very unlikely to have time to do release
>
> > managing after the 1.2.7 release until spring (luckily it's for
>
> > fortunate-to-me reasons).
>
> >
>
> > Despite the delay in schedule on this release, generally doing a
>
> > maintenance release is relatively low effort. These kinds of
>
> > "substitute RM" situations are a great chance to get familiar with the
>
> > process while having a well-defined end point. If there's anyone who'd
>
> > like to give it a try by handling things while I'm gone, both I and
>
> > I'm sure the project community would be grateful.
>
> >
>
> > To take on this particular task, one must be a committer already (due
>
> > to ASF policy). It's a great way to "act like a PMC" for those
>
> > committers who'd like to make a long term investment in HBase.
>
> >
>
> > Anyone interested?
>
> >
>
> > -busbey
>
> >
>
> > [1]: https://issues.apache.org/jira/browse/HBASE-18276
>
> >
>
>
>
>
>
>