Hi Hop developers, I would like to have a short discussion about the proposed release date for our 2.6 release. Currently we are following a 2 month release cycle but I would like to propose to extend the window a bit for our 2.6 release.
If we follow our current schedule the cut-off date for 2.6 would be 28 July with a release in the first week of august. As this is dead center of the usual holiday season for a bunch of the people working on the project I would propose to extend 2.6 to the end of august and release the beginning of september. This would also shift the following releases to November making 2.7 the last release of 2023 (this also means we do not have to try and make a release during the end-year period) Any thoughts on this? Cheer, Hans
