Hi Andy, 

I finished the coding. I’m preparing the documentation and I will prepare the 
patch. 

In schedule that I presented in my document, the forecast for the end of the 
project was 29. In the remaining time, I wish to implement an engine to 
evaluate rules with Sparql commands combined with rule terms, as suggested by 
Dave. If the project must finish until 18, I will do in the same,  outside of 
project. 

Miguel

On 12 Aug 2014, at 16:27, Andy Seaborne <a...@apache.org> wrote:

> On 06/08/14 16:47, Miguel Bento Alves wrote:
> ...
>> "There is one piece of wrapping up which is to make sure that you have the 
>> latest jena-core code, prepare a patch file that captures your chnages and 
>> additions then attach to the GSoC JIRA.”
>> Ok, I will do that.
>> 
>> Miguel
> 
> Just a reminder - we're in the wrap-up week, with 18 August being the firm 
> 'pencils down' date so preparing the patch is the critical item this week.
> 
>       Andy
> 
> 