Varun Thacker created SOLR-8412:
-----------------------------------
Summary: SchemaManager should synchronize on performOperations
method
Key: SOLR-8412
URL: https://issues.apache.org/jira/browse/SOLR-8412
Project: Solr
Issue Type: Bug
Reporter: Varun Thacker
Priority: Minor
Currently SchemaManager synchronizes on {{schema.getSchemaUpdateLock()}} . We
should synzhronize on {{performOperations}} instead.
The net affect will be the same but the code will be more clear.
{{schema.getSchemaUpdateLock()}} is used when you want to edit a schema and add
one field at a time. But the way SchemaManager works is that it does bulk
operations i.e performs all operations and then persists the final schema . If
there were two concurrent operations that took place, the later operation will
retry by fetching the latest schema .
--