Hi,
yesterday Jakob and me we were talking about the possibility to plan the
next release by the end of July 2013. I think we have made an important
progress in many parts of the project, but we should try to reflect
those things as releases.
Taking a quick look into our issue tracker:
https://issues.apache.org/jira/issues/?jql=project%20%3D%20MARMOTTA%20AND%20fixVersion%20%3D%20%223.1-incubating%22%20AND%20status%20in%20(Open%2C%20%22In%20Progress%22%2C%20Reopened)%20ORDER%20BY%20priority%20DESC
Currently there are 55 issues planner for that version. For me it's
quite clear that we would need to prioritize some of them, and shift
some to 3.2. So I think all current assignees should decide what to do
with their issues by 3.1.0, trying to balance priority and the time they
would have to take care of those issue.
What do you think? Would be feasible?
Cheers,
--
Sergio Fernández