Sorry, am I missing something? How do we end up with a cycle in Continuum? Is there a specific example?

I know it's possible - we had to allow it in the repository (eg, dom4j <-> jaxen), but it is certainly undesirable and honestly should be rare, especially in m2 built artifacts. Should it produce a build warning?

Basically, the treatment there is to just stop following the tree when you hit the cycle, rather than changing the way things are ordered. So it's really arbitrary which might come first, but isn't really a concern there.

Anyway, just wondering.

Cheers,
Brett

On 08/11/2006, at 11:46 PM, Emmanuel Venisse wrote:

Yes

Jesse McConnell a écrit :
we should add a page that analyzes each schedule for cycles...that
would be a cool little feature
On 11/8/06, Emmanuel Venisse <[EMAIL PROTECTED]> wrote:
Yes, we need a global ordering, so projects will be build independently of groups, because in some case a cycle can be created between groups (not necessary between projects).

In case a cycle is detected between projects, continuum can't find the build order. In this case, I think we need to sort a little project so will reduce build errors. So if we have a cycle, we can sort projects in a group and build them. In most of case (maven projects), we don't have a cycle in
a group.

Emmanuel

Brett Porter a écrit :
> I think you want global ordering. Grouping should just be a
> display/management technique, not anything that changes how projects are
> handled.
>
> However, this needs to be reviewed as a whole (which I think Emmanuel is > doing), such that builds can be triggered when their dependencies change > which will help with the ordering as it won't be dependant on them all
> being triggered at the same time?
>
> - Brett
>
> On 08/11/2006, at 9:51 AM, Jesse McConnell wrote:
>
>> I was reading through the DefaultContinuum.buildProjects ( Schedule id >> ) method and after discussing some things with Emmanuel...I think we >> have a problem here. When I went through and refactored things to >> support a more Project Group centric setup with continuum I changed
>> this method a bit.
>>
>> Originally, this method would gather up all projects that would be >> triggered by that schedule, run them all through the project sorter
>> and then build each in sequence.
>>
>> When I added the project groups to this mix, I changed things to be on >> a project group basis, so that on a project group by project group
>> basis it would order the projects and build them.  At the time I
>> thought this was the way to go...but maybe not.
>>
>> 17:14 <evenisse> we need to take all projects from all groups, sort them >> 17:15 <evenisse> if we don't have a cycle, it's ok and we build all
>> 17:15 <evenisse> if it isn't ok, we sort project by group
>>
>> For example, if we loaded up a Plexus group and a Maven group...the >> way it currently is (with my change) it would process all triggered >> builds within one group and then process all triggered builds in the >> other group. This would not take into account potential dependencies
>> between the two.
>>
>> Does anyone have any thoughts on this? I am inclined to fix it up so >> its like it used to be where all projects across all project groups
>> are thrown into the graph....I keep feeling like I am missing
>> something wrong with this, but I can't pin it down.
>>
>> One thing that perhaps Emmanuel could explain a bit more is the third >> comment there. In our conversation on this he said that he thinks >> that the cycles are cropping up all the time, and if thats the case >> then we are building a lot of unordered builds which would account for >> some of the strange reports we have been getting. Are you saying that >> if we detect the cycle we default back to the way I am doing it now?
>> order within the groups...
>>
>> jesse
>>
>>
>>
>>
>>
>> --jesse mcconnell
>> [EMAIL PROTECTED]
>
>
>


Reply via email to