Can I ask the community to check the last project Task status proposal?
If there are no further comments i will implement the proposal below in
a couple of days in the special component 'project manager'

The final proposal about the project task status was:

The status on a task is largely system controlled (1-4) and user controlled 
(5-6):
----------------------------------------------------------------------------------
1: unassigned   -> the task has no performers and has not started.
2: assigned     -> the task has one or more performers but has still not started
3. in-progress  -> at least one performer has registered, the task is started
                                 time on the task
4. completed    -> all attached performers have set their assign
                        status to completed
5. onHold       -> the projectmanager can set this status and 
                        can be set back to status 1-3
6. cancelled    -> again can be set by the projectmanager

The status of the assignment of a party to the task is manual
controlled:
-------------------------------------------------------------
1. assigned     -> the task is assigned to the party with 
                        from/thru dates to show when active
2. completed    -> the party has done his part (work,approval,
                  test etc) on the task and has indicated he is ready.


-- 
http://Antwebsystems.com : OFBiz Quality support for competitive rates.