Tim Ruppert commented on OFBIZ-796:
-----------------------------------

I totally agree.  Let's restate the 5% Hans, so that we can ensure that we fill 
in these gaps.  Since you're the most knowledgeable on this issues, please just 
walk thru each of the original requests and direct people to where they are 
implemented, or indicate that they're not, so that people can start addressing 
those issues.

> WorkEffort Application aka Project Management Application
> ---------------------------------------------------------
>
>                 Key: OFBIZ-796
>                 URL: https://issues.apache.org/jira/browse/OFBIZ-796
>             Project: OFBiz
>          Issue Type: Improvement
>          Components: workeffort
>            Reporter: Amit Shinde
>            Assignee: Anil K Patel
>         Attachments: ProjectMgr.patch
>
>
> WorkEffort Application aka Project Management Application -
> Objective -
> 1.> make project planning/organization easier and intuitive,
> 2.> process requests in a better way,
> 3.> improve iteration planning,
> 4.> include ability to integrate seamlessly with invoices/billing ,
> 5.> generate detailed and snappy reports,
> 6.> send email/ mobile notifications.
> Process -
> Project Tree -
> 0 - Project/s (WE)
>                 1 - Sub Project/s (WE)
>                               2 - Task/s (WE)
>                                           3 - Sub-Task/s (WE)
>                 1 - Task/s (WE) - These are not assigned to any sub-project
> 0 - Task/s - These are not assigned to any project
> 0 - Request/s-
>                 1 - Request Item/s
> - Projects, Sub-projects and Tasks all are WorkEfforts of a respective type. 
> - Request is a CustRequest and can have many Request Items.
> - Time Entry can be done from any level or type of WE
> - Requests and WorkEfforts have many-to-many relationship
> Effort - 
> Most of the screens and models are already in place. We definitely dont need 
> any changes in the models. We need to add new screens, forms and services. 
> Heres a list of todos -
> Create Demo data of a project - I am working on this one right now. This will 
> be helpful for reports. We can import this and pick any of the reports and 
> start implement them.
> Create Reports Menu page - Adrian Crum has helped with this. 
> Reports - These are planned to be pdfs but to start with we can start 
> implementing them in HTML.
>  1.  Task by priority (Iteration planning), - Amit
>  2  Task over time estimate,  
>  3. Project summary  (By Supervisor / By Client), 
>  4. Gantt for Project, 
>  5. Tasks of type project, 
>  6. Tasks completed, times task was reopened,  Avg. time taken to fix a task 
> , Avg.  number of tasks fixed per day, - Amit
>  7. WE estimate versus actual. 
> UI - All these screens will be in HTML.
>  1.  Tasks assigned to me, - Amit 
>  2.  Tasks not assigned, dropdown/popup assign to X
>  3.  Tasks not scheduled
>  4.  Tasks past schedule
>  5.  Estimated schedule/ workload for me
> Email notifications -
>  1.  Tasks assigned to me
>  2. Weekly project summary
> Mobile Notifications -
> 1. Send SMS alert on any event. - Need to do more research.

-- 