Hi All,

We continue doing the AOO 4.1 Function Verification test(FVT), here is the
weekly update (2/10 - 2/14):

*Test execution:*
1. Template validation - Ongoing
Question: A new .odp is created with the template when try to open .otp
file, is it intended?
Issue: only the first slide in template is available for apply to the
existing presentation in AOO

2. Existing feature on 3 APP testing - Ongoing
We have assigned 817(673 as of 1/24) test executions to about 39(28 as of
1/24) volunteers, and completed about 39.4%(23% as of 1/24) in execution
(461 test executions done, 250 as of 1/24). We get 11 more test execution
volunteers since Jan 24, although the target date to complete FVT is moved
to Feb 24, we need to remind volunteers in this week


    Total    Not Run    Passed    Failed    Blocked    Completed [%]
Debian Linux 64bit    56    7    36    10    3    87.5
MacOS X    209    144    49    14    2    31.10
Redhat Linux 32bit    69    67    0    2    0    2.90
Redhat Linux 64bit    277    143    98    32    4    48.38
Ubuntu Linux 64bit    167    111    47    9    0    33.53
Windows 7    209    109    75    22    3    47.85
Windows 8    182    127    41    14    0    30.22
Total    1169    708    346    103    12    39.4

*Defect summary:*
1. Summary of resolved issues in Bugzilla, about 28 issues are (severity =
blocker or critical)
https://issues.apache.org/ooo/buglist.cgi?cmdtype=dorem&list_id=125237&namedcmd=AOO_Need_Verify_4.1&remaction=run&sharer_id=249289

*Issues & quality highlight:*
1. We need to remind test execution volunteers to complete their
assignments before Feb 24, as it is one week left
2. We have execution gap in FVT test as lack Mac text execution volunteers
in testing, have sent the call in forum for test execution volunteers on
Mac and other platforms(except Linux Redhat 64bit)

*Volunteer status: *
1. 11 new test execution volunteers(total 39 so far) joined on FVT
execution work since Jan 24
2. Need defect volunteers to verify high priority issues in Bugzilla (see
above in Defect summary)

*Plan for next week:*
1. Continue to do FVT test on Mac, Linux and Windows
2. Start to verify high high priority issues
3. Continue to do template validation

Thanks you all for effort since Jan 24, we have one week left to FVT target
date(Feb 24), let's continue and make progress next week!

Regards,
Yu Zhen