[ https://issues.apache.org/jira/browse/PIG-1883?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel ]
Thejas M Nair updated PIG-1883: ------------------------------- Attachment: PIG-1883.4.patch I have made some fixes to the way the progress logging is handled when both old and new timers are enabled. I have also removed the -s command line option to control the behavior, and replaced with the use of a new property. This is because -s option will be deprecated in future. > Pig's progress estimation should account for parallel job executions > -------------------------------------------------------------------- > > Key: PIG-1883 > URL: https://issues.apache.org/jira/browse/PIG-1883 > Project: Pig > Issue Type: Improvement > Reporter: Laukik Chitnis > Assignee: Laukik Chitnis > Attachments: PIG-1883-2.patch, PIG-1883-3.patch, PIG-1883.4.patch > > > Currently, Pig's progress estimation is based on the percentage of jobs > completed out of the total number of MR jobs. However, since the MR operators > are arranged in a DAG (and hence more than 1 job might be submitted for > execution in parallel), the progress estimation can be improved by > considering the number of jobs in the critical path, instead of just the > total number of jobs. -- This message is automatically generated by JIRA. For more information on JIRA, see: http://www.atlassian.com/software/jira