Thejas M Nair updated PIG-1883:
-------------------------------

    Attachment: PIG-1883.4.patch

I have made some fixes to the way the progress logging is handled when both old 
and new timers are enabled.
I have also removed the -s command line option to control the behavior, and 
replaced with the use of a new property. This is because -s option will be 
deprecated in future.

> Pig's progress estimation should account for parallel job executions
> --------------------------------------------------------------------
>
>                 Key: PIG-1883
>                 URL: https://issues.apache.org/jira/browse/PIG-1883
>             Project: Pig
>          Issue Type: Improvement
>            Reporter: Laukik Chitnis
>            Assignee: Laukik Chitnis
>         Attachments: PIG-1883-2.patch, PIG-1883-3.patch, PIG-1883.4.patch
>
>
> Currently, Pig's progress estimation is based on the percentage of jobs 
> completed out of the total number of MR jobs. However, since the MR operators 
> are arranged in a DAG (and hence more than 1 job might be submitted for 
> execution in parallel), the progress estimation can be improved by 
> considering the number of jobs in the critical path, instead of just the 
> total number of jobs.

--
This message is automatically generated by JIRA.