> On 5 Jan 2016, at 03:44, Josh Elser <[email protected]> wrote:
> 
> Sweet. This is great! Thanks for taking the time to write up the docs.
> 
> Since I have some investments in our next release, I will preemptively 
> volunteer to handle the next one. :)
> 
> Mid-February/Early-March? Shall I update the JIRA version?

how about March 1?

> 
> Steve Loughran wrote:
>> for the curious (and whoever has to do it next), this is our current release 
>> process
>> 
>> http://slider.incubator.apache.org/developing/releasing.html
>> 
>> it's essentially a mix of: property-driven and targets and manual steps 
>> between them. Ant can do things like invoke maven, play with git and svn, 
>> validate URLs and generate the various emails. Humans have to do the dull 
>> bits in between: posting the emails, collecting the results, pressing 
>> buttons on JIRA, Nexus and Apache CMS.
>> 
>> The final actions to build the incubator vote result, commit the RC to a 
>> release and issue the announcement still need to be tested/debugged/fixed 
>> —once done I think we have the release process pretty much locked down to 
>> the extent that a new RC can be cut in under an hour, with the other steps 
>> adding up to ~3 hours work spread over the days needed for votes to complete.
>> 
>> Which means....we can think about a release process of 6-8 weeks. I'd almost 
>> say "monthly" were it not for the double vote overhead; there'd only 
>> effectively be 2 weeks between the public release of one version and the 
>> starting of a vote on the next. 6 weeks would allow time for bugs to surface
>> 
>> -steve
> 

Reply via email to