BTW - the merge window for 1.6 is September+October. The QA window is
November and we'll expect to ship probably early december. We are on a
3 month release cadence, with the caveat that there is some
pipelining... as we finish release X we are already starting on
release X+1.

- Patrick

On Thu, Oct 1, 2015 at 11:30 AM, Patrick Wendell <[email protected]> wrote:
> Ah - I can update it. Usually i do it after the release is cut. It's
> just a standard 3 month cadence.
>
> On Thu, Oct 1, 2015 at 3:55 AM, Sean Owen <[email protected]> wrote:
>> My guess is that the 1.6 merge window should close at the end of
>> November (2 months from now)? I can update it but wanted to check if
>> anyone else has a preferred tentative plan.
>>
>> On Thu, Oct 1, 2015 at 2:20 AM, Meethu Mathew <[email protected]> 
>> wrote:
>>> Hi,
>>> In the https://cwiki.apache.org/confluence/display/SPARK/Wiki+Homepage the
>>> current release window has not been changed from 1.5. Can anybody give an
>>> idea of the expected dates for 1.6 version?
>>>
>>> Regards,
>>>
>>> Meethu Mathew
>>> Senior Engineer
>>> Flytxt
>>>
>>
>> ---------------------------------------------------------------------
>> To unsubscribe, e-mail: [email protected]
>> For additional commands, e-mail: [email protected]
>>

---------------------------------------------------------------------
To unsubscribe, e-mail: [email protected]
For additional commands, e-mail: [email protected]