since it was time to submit a report, I did submit the drafted report
to the board.

The next report should be on schedule in March 2014.

Best,
 - Fabian


2014/1/6 Fabian Christ <christ.fab...@googlemail.com>:
> Hi,
>
> here is a draft for our board report that needs to be submitted ASAP.
> The board meeting is scheduled for Jan 15, 2014.
>
> Please comment, add.
>
> Status report for the Apache Stanbol Project - January, 2014
>
> Apache Stanbol provides a set of reusable components for semantic content
> management.
>
> The project missed to report on their regular schedule in December 2013,
> therefore this report was prepared for January 2014.
>
> There are no issues which require board attention at the moment.
>
> The project is performing well and new features are added on a regular basis.
> The dev mailing list is actively in use. Requests from subscribers are handled
> promptly.
>
> The release process is still slow which means that the project was unable
> to produce a release since Feb 2013. The reason seems to be that release
> preparation is to time consuming and there are not enough committers that
> are capable of performing a release.
>
> As a consequence the current Stanbol users mostly rely on the latest versions
> from the dev trunk or the already existing release branch. The project is
> aware of this situation and is working on that issue.
>
> Subscribers on the dev list: 210
> No new committers were elected since June 2013.
>
> No releases were published.
> Last release was: apache-stanbol-enhancement-engines-0.10.0 on Feb 2nd, 2013
>
>
> --