On 20.02.2014, at 14:47, Diederik de Haas <[email protected]> wrote:

> On Thursday 20 February 2014 14:40:24 Frank Karlitschek wrote:
>> - 26.2. Release of RC1
>> - 28.2. Release of final 6.0.2 tar file to packagers
> 
> Why is there (always) such a short period between a beta/RC and the final 
> release?
> This hardly gives ppl a chance to install and test it and/or figure out 
> what/where/why things went wrong and to report it and have time to fix it.

Hi Diederik,

thanks for the feedback! Unfortunately we have a timing challenge here. But we 
can do the RC1 one day earlier. So the schedule looks like that:

- 24.2. All fixes have to be backported to stable6
- 25.2. Release of RC1
- 28.2. Release of final 6.0.2 tar file to packagers
- 3.3.  6.0.2 release

Does this work for everyone?


Frank




> Regards,
>  Diederik
> -- 
> GPG: 0x138E41915C7EFED6_______________________________________________
> Packaging mailing list
> [email protected]
> http://mailman.owncloud.org/mailman/listinfo/packaging

_______________________________________________
Devel mailing list
[email protected]
http://mailman.owncloud.org/mailman/listinfo/devel