currently the master scheduling that im running here create 1 planned
order to fulfill each requirement. With the
item's purchase qty multiple set as 5, it create 1 planned order of 5
to fulfill a small requirement (e.g.0.001).
consequences are so many planned orders created (even in same day of
requirement) and qty is much more exceeded.

my expected result is system create 1 planned orders to fulfill some
requirements based on period, to propose more
logical planned orders to users.

i have coverage code in coverage group setting set as "Period" and
cov period set as 7.

pls advice which parameters else i should consider to solve this
problem.

thx in advance.


daniel